Status Update - 5/2/19
May 2, 2019
| Status Item | Current Status | Previous Status | Comment |
| Schedule | red | red | Banner Integration Delay |
| Resources | yellow | green | Departure of a Huron resource |
| Financials | green | green | |
| Quality | green | green | |
| Project Issues | red | red | Banner/Axiom Integration data load is delayed |
| Key Deliverables | % | Comments | Timeline |
| Requirement Sign-off | 100% | 12/14 | |
| Data Model/Mapping | 100% | 1/12 | |
| Build | 100% | 4/19 | |
| Integration | 55% | Loaded: Accounts, Plans, Contacts, Address, Relationships, Affiliations, Terms, Communications, Comments | 5/3 |
| Training/UAT | 0% | Training and UAT dates delayed | 5/14 |